From August 5th, Italian PV plants above 100 kWp up to 10 MWp (Medium Voltage) must comply with stricter ARERA (Autorità di Regolazione per Energia Reti e Ambiente) requirements. This new regulation, ARERA resolution 385/2025, which is part of the CEI 0-16 standard, creates an urgent need for operators and installers to ensure reliable grid integration.
Obton unveils Advanced Global Monitoring Centre in Milan
Previously, this requirement applied only to larger plants of 1 MWp and above. To facilitate a seamless transition, meteocontrol has introduced a comprehensive, integrated solution. The system, combining a Power Plant Controller (PPC or CCI – Controllore Centrale di Impianto in Italian) with blue’Log, delivers several key benefits. Not least, it enables grid conformity without dependence on third-party solutions or external portals and provides a compatible all-in-one setup that includes the “PF2” controlling feature. (hcn)