A bank’s evaluation does not begin with the modules, inverters or grid connection. “Whether we finance an agrivoltaic project is decided first on the basis of the farming and only then on the basis of energy production,” said Laetitia Limongi, head of structured finance for renewable energy at the French bank Banque Populaire du Sud. “The energy project has to serve the agricultural project. The other way around does not work,” she told this year’s Agrivoltaics Industry Forum, organised by Conexio PSE in Bordeaux.
Adapting to farming
This means that agricultural production has to be planned first. The solar installation can then be adapted to that production. In agrivoltaics, agricultural use is the foundation on which the entire project rests, both legally and economically. “This agricultural use must also be able to evolve, without the solar installation constraining that development,” says Limongi.
That flexibility matters because an agrivoltaic installation is designed for a service life of 25–30 years, and a great deal will change on the site over that period. Water availability shifts, the climate changes and the farm itself develops its business model and production methods. “A farm that can no longer adapt within three decades becomes a structural risk for the entire financing,” Limongi said.
Allowing for different crop rotations
A solar installation designed for a single crop, a single rotation or a specific form of cultivation ties the farmer to a rigid concept for decades, which makes the project harder for the bank to assess. Solar structures therefore have to accommodate different crop rotations, and a wide range of agricultural machinery must be able to operate under or between them in the future. “We need to see that the farmer will still be able to work the land in twenty years, even if they are then growing something entirely different,” Limongi said, naming one of the central criteria.
Double harvest from field and pasture – solar income for farmers
Meeting the rules over the long term
Projects must also meet statutory requirements, which typically set out how much land must remain available for agriculture or what level of agricultural yield an agrivoltaic project has to deliver. In France, agrivoltaic land must produce at least 90 percent of the yield of a comparable reference plot without agrivoltaics, and similar minimum thresholds exist in many European countries. “The range runs from around 66 percent in Germany to 90 percent in France,” Limongi said. Rules on permissible technologies apply as well, and these usually concern the mounting height of the modules.
Maintaining agrivoltaic status
For the bank, it is not enough that an installation meets these requirements at commissioning. State authorities generally carry out regular checks during the operating period, so agricultural yield determines the installation’s status for decades. “If a project loses its agrivoltaic status over the years, significant financial and regulatory consequences follow,” the banker warns.
EnergyDecentral: storage and power marketing gain ground with farmers
The two requirements are closely linked. If the farming operation cannot adapt to changing conditions, yields fall and the minimum agricultural yield comes under threat. “Without adaptable farming and without lasting compliance with the regulatory framework, no project will secure long-term financing,” explains Limongi.
Banks need reliable data
To assess these risks, a bank needs reliable data, and at present that data is still lacking. Few studies track the development of crops under modules over longer periods, and insights into how different mounting systems affect the cultivation of the land remain rudimentary. “We therefore need more standardisation, more operating data and more feedback from installations in service,” Limongi said. Banks find it harder to finance a concept that has not yet been sufficiently tested than an approach backed by established experience. “Proven use cases are one of the most important signals for us that a project is bankable,” she added.
Agrivoltaics Industry Forum 2026: big gains call for clear rules
That makes scientifically monitored projects all the more important. The more of them there are, the broader the pool of experience and the closer banks come to the data they still largely lack. Every project seeking financing stands to benefit, since each additional year of operating experience makes the models more reliable and projects easier to finance.
The second part of our series on financing agrivoltaic projects, out next week, looks at how banks assess revenues, contracts and additional components such as storage, self-consumption and energy communities. (su)