Opinion: Solar developers should say “no” sooner

Solar development pipelines keep growing. At PVcase, which makes software for designing solar projects, we surveyed professionals this summer in Germany, Italy, Spain and the US, and 91 percent reported a growing pipeline over the past 12 months, up from 84 percent a year earlier.

Yet more of those projects are dying on the way. In our 2026–27 survey of 405 solar professionals, 46 percent of respondents said at least half of their projects never reach construction. A year earlier, 32 percent said the same. As our report puts it, “the industry is originating more projects and abandoning a larger share of them than it was a year ago.”

Failing early, failing cheaply

Some attrition is healthy, since not every site deserves to become a power plant. What matters is when a project fails. A site ruled out in its first weeks costs very little. A project abandoned later has often consumed land options, interconnection deposits, environmental studies and engineering hours that can never be recovered. No wonder half of the senior executives we surveyed named attrition as one of their highest controllable costs.

Solar Investors Guide – New trends in PV projects

And late is where the losses pile up. Respondents named financing (42 percent) and permitting and grid connection (37 percent) as the stages where projects face the greatest setbacks, against 20 percent for site selection. Finance (74 percent) and regulation (70 percent) remain the leading causes of failure, while community opposition rose fastest, from 43 to 57 percent. Failure rates also vary across Europe’s markets. Half of Italian respondents said at least half of their projects never get built, compared with 48 percent in Germany and 44 percent in Spain.

The causes differ too. In Germany, community opposition is now the top-cited single reason for failure, named by 32 percent of respondents against 20 percent globally. In Italy, 42 percent name regulation as a main reason, the highest score for any single cause in any market. In Spain, external stakeholder management is cited by 75 percent and grid interconnection by 63 percent. Most of these risks are visible from the start. A grid constraint, a land-use rule or a sceptical community can usually be spotted before the first layout is drawn. In most cases, developers have the data but put off the decision.

A data problem, but not a lack of data

So why do we keep deciding late? In my view, the answer is fragmentation. The information needed for an early call exists, but it is scattered across tools, teams and spreadsheets. The average company now uses eight software tools across a project’s life, up from 6.8 a year earlier, and Italy’s stack is the heaviest, at 8.5. Two-thirds of respondents (67 percent) cite the absence of a single source of truth as a workflow bottleneck, the most frequently named in the survey, rising to 71 percent in Italy.

Opinion: the jobs asset managers can safely hand to AI

Fragmentation also has a measurable cost. The share naming project data and information management as a cause of failure rose by 9 percentage points, to 44 percent. When the grid study sits in one file, the land assessment in another and the financial model in a third, nobody sees the whole picture until the money has already been spent.

A five-question test before engineering starts

As our report puts it, the industry has industrialised the act of building solar farms, but not the act of deciding which ones to build. In practice, I would put every new site through five questions before a single engineering hour is booked:

Grid: can we name a realistic connection point, capacity and date, and a rough cost for upgrades?

Land and environment: is any part of the site ruled out by protected areas, land-use rules or ground conditions?

Permits: do we know which permits we need, who issues them and how long they take locally?

People: do we know who the neighbours and local stakeholders are, and what they think?

Money: does the project still work under cautious assumptions about prices, curtailment and connection costs? The rule that goes with it is simple. One “no” ends the project. One “we don’t know” means it is not ready for engineering spend. And the answers must sit in one place that everyone in the decision can see, including the commercial, engineering and finance teams.

That is why we built PVcase Concept, the software we launched at RE+ 2026 in Las Vegas. It brings site boundaries, constraints and project assumptions into one place, generates preliminary layouts, including for battery storage, and compares options on capacity, yield, CAPEX and levelised cost of electricity (LCOE). Weak sites drop out before detailed engineering starts, and promising ones move into PVcase Ground Mount without having to rebuild the data.

Saying no is how more solar gets built

Saying no sooner is not pessimism. It protects the resource that matters most. In our survey, 95 percent of professionals identified high-quality engineering as the most important factor in project success. Every engineering hour spent on a project that should have been stopped is an hour taken from one that should be built.

What Europe needs is fewer late failures, and the solar projects themselves can keep coming. The faster each site moves from maybe to a clear yes or no, the more of our pipelines will turn into megawatts. (David Trainavicius/hcn)